Culinary Water Project Update
The LaVerkin City Culinary Water Improvements Project 2010 is in full swing...
The project's main focus is to replace the old State Street culinary line, but also has some side-street work included. A new 8" culinary line has been installed in 400 N. The old 6" line will become an irrigation line in the future. The hydrant has been moved to connect to the new line, and a valve has been installed. New culinary lines have been laid in 125 W. and 630 N. as well. Pipe will also be installed from Bringhurst Lane on the Toquerville border to the bridge near the River Wood Subdivision on LaVerkin's northern boundary.
The project has a time line of 75 days for completion and is under contract with Hawker Enterprises.